Live From The Charlotte

Get the latest update with live streaming of
The Charlotte construction progress!

CRANE EAST
CRANE WEST
CAMERA EAST
CAMERA WEST
CAMERA NORTH


Update from the Construction Team

March Highlights

  • The second floor zone 1 suspended slab has been formed, reinforced, mechanically and electrically roughed-in, and has had the concrete placement completed.
  • The ground to second floor zone 2 column and shear wall reinforcement, forming, and concrete placement processes have been completed.
  • The second floor zone 2 suspended slab has been formed, while the reinforcement and mechanical and electrical rough-ins are well underway.
  • The second to third floor zone 1 columns and shear walls have been reinforced, formed, and have had the concrete placement completed.
  • The main storm service riser stacks have been installed within the P3 and P2 parking levels.
  • The precast stairs have been installed within all stairwells, at all parking levels.