Live From The Charlotte

Get the latest update with live streaming of
The Charlotte construction progress!

CRANE EAST
CRANE WEST
CAMERA EAST
CAMERA WEST
CAMERA NORTH


Update from the Construction Team

July Highlights


    • P1 electrical and hydro-vault rooms have been painted, with their doors and hardware installed.
    • Ground floor exterior framing, gypsum sheathing, and window blocking installation are complete and the second floor is underway.
    • P3 level wall and stair patching process have been completed, while the block-work is well underway.
    • Fifth-floor curbs and upstand walls have been formed, reinforced, and poured.
    • Ninth floor suspended slab mechanical and electrical rough-ins and reinforcement, and concrete placement has been completed.
    • Eighth-floor zone 2 suspended slab has had the concrete placement completed; it has also been patched to accommodate the waterproofing membrane application.
    • The eighth to ninth-floor verticals have been reinforced, formed, and have had the concrete placement completed.
    • The ninth to tenth-floor verticals have been reinforced and are currently being formed.

Upcoming Highlights


    • The parking level pressurization ducts are to be installed and inspected.
    • The P2 block work, paint, and the doors and hardware installation is to commence.
    • The ground floor window frame installation is to commence.
    • The ground floor block work and fire stopping is to be completed; the same could be noted regarding the interior layout. That of the second floor is to commence.
    • The sixth floor curbs and upstand walls are to be formed, reinforced, and poured. Those on the seventh floor are to commence.
    • The tenth floor suspended slab mechanical and electrical rough-ins and reinforcement, and concrete placement are to be completed.
    • The elevator machine room roof slab is to have the forming, reinforcing, and concrete placement completed. The divider beam installation is to commence.
    • The pool outer liners waterproofing and insulation are to be completed, with the base form work and reinforcement to commence.
    • The tenth to eleventh floor verticals reinforcement and formwork to commence.